2nd SCOM Meeting

At the second meeting of the Steering Committee, the contract with the ATG Giurgiu Shipyard was signed, for the provision of dredging equipment, which will contain the following: a dredge, two split-barges, a technical assistance vessel and a pontoon for the installation to load the split-barges.
The dredge is without an engine, but equipped with a moving installation, has a capacity of 700 cubic meters per hour. the on-board equipment ensures to monitored the dredging pressure and positioning. They are state-of-the-art equipment, being developed and sized by a company with experience in this activity.

  • The design of the technical assistance vessel is presented and it is specified that it will be used for mounting the discharge pipeline, as well. The split-barges are without an engine, with a capacity of 400 m3 and will transport the dredged material.
  • The pontoon will have a pillar lifting system, which will be used to be position.
  • The discharge pipe will be of a maximum 500 m, given that the analysis of the area showed that no longer length is needed.